July 1, 2008 - June 30, 2009
Updated 11/6/08
|
Program |
Action Plan / Goal |
Status |
|
ADM Adminstration |
Complete all identified administrative
requirements by June 30, 2009 |
On track |
|
ADM Annual Meeting |
Hold Annual Meeting by February 28, 2009 |
On track |
|
ADM Budgeting |
Develop and adopt budget for FY 09-10 prior to
June 30, 2009 |
Scheduled for 2/26/09 |
|
ADM District Capacity |
Complete at least 3 actions to improve the
capabilities of this and other OR SWCDs by June 2009 |
On track |
|
ADM Safety |
Maintain high level of safety awareness and
remain accident free during the entire year. |
On track |
|
GEN Ag
Sustainability |
Provide at least 4 learning opportunities for
farmers and ranchers to on methods to improve soil quality by June 09. |
On track |
|
Gen Bakeoven WASCOBs |
Assist Conroy Ranch construct at least 3 WASCOBs
in Bakeoven Wate4rshed by 6/30/09 |
On track |
|
GEN Backyard Conservation |
Conduct a backyard xeriscaping workshop by
10/30/08 |
Completed |
|
GEN CAFO |
Assist private landowners in complying with State
confined animal feeding operations regulations. |
On track |
|
GEN Conservation Equipment |
Make mower and mulcher available to area
producers during the year |
On track |
|
GEN CRMP |
Make use of Coordinated Resource Management
Planning (CRMP) process in |
On track |
|
GEN District Cost Share Pgm |
Implement District Cost Share Program with at
least 12 projects by June 2009 |
On track |
|
GEN Dry Crk Habitat Restor. |
Install 20 instream habitat structures on Dry
Creek by December 2008. |
Behind |
|
GEN Farm Bill Support |
Implement current Farm Bill Programs, by
promotion, technical assistance, and reporting through June 2009 |
On track |
|
Gen Fifteenmile Monitoring |
Develop comprehensive Resource Monitoring
Proposal for Fifteenmile Creek Watershed by December 2008. |
Behind |
|
GEN Indian Creek Juniper |
Develop Indian Creek grazing and burn plans and
Initiate Juniper control project by December 2008. |
On track |
|
GEN Irrigation Ditches |
Provide assistance to Irrigation Districts in the
|
On track |
|
Gen Juniper Flat Tech Assistance |
Assist Juniper Flat DIC determine extent and
locations of water losses by June 2009 |
On track |
|
Gen Marshall Irrigation Upgrade |
Assist R. Marshall convert flood irrigation
system to center pivot by June 2009 |
On track |
|
GEN Mosier Groundwater Study |
Work with USGS to wrap up Mosier Groundwater study and prepare Action
Plan by June 2009 |
Behind |
|
GEN Monitoring, multi-project |
Complete Annual Monitoring Requirements for Previously
Completed Projects by 6/4/09 |
On track |
|
GEN No Till |
By 12/30/08 complete direct seed conversions on 500
ac. under the |
On track |
|
GEN Nursery |
Maintain plantings and equipment at H.A. Miller
Demonstration Nursery through June 2009 |
On track |
|
Gen Orchard Workshop |
Conduct a large beneficial organisms workshop for
area orchardists by 10/30/08 |
Completed |
|
GEN Pig Control Project |
Support interagency efforts toward feral swine
eradication through June 2009 |
On track |
|
GEN Rock Creek piping design |
Complete Rock Creek Ditch piping system design
project by 3/1/09 |
Behind |
|
GEN Small Grant Program |
Assist local Landowners obtain small grants and
implement at least 5 projects by June 2009 |
On track |
|
GEN Steelhead habitat |
Install instream habitat structures on lower
Fifteenmile Creek by October 2008 |
Cancelled – no funding |
|
GEN Stump Grinding Demo |
Completed Stump Grinding Demonstration by Dec. 2008 |
Completed |
|
GEN Plant Materials |
Get at least 40,000 Conservation Trees and Shrubs
planted by May 1, 2009 |
On track |
|
|
Install Bridge at Turner Ranch on Eightmile Creek
by December 1, 2008 |
Cancelled by landowner |
|
|
Initiate Juniper control and range improvement
project at Wapanitita by December 2008 |
Delayed pending grant |
|
GEN WYEAST RC&D Support |
Provide organizational support to WyEast RC&D
Area Council through June 2009 |
On track |
|
IEM Conservation Awards |
By November 3, 2008 submit at least 7 nominations
for the |
Completed |
|
IEM Marketing |
By June 30, 2009, publish at least twelve
articles on the SWCD and its accomplishments in |
On track |
|
IEM Newsletter |
Distribute at least six bi-monthly issues of
Groundwork by June 2009 |
On track |
|
IEM Public Information |
Participate in at least 36 public information
activities by June 2009 |
On track |
|
IEM Rural Living Handbook |
By February 2009 Develop, Print, and Distribute at least
2,000 Wasco County Rural Living Handbooks |
Behind |
|
ORP CREP buffers (CP) |
Establish 10 riparian buffers in Lower
Deschutes/John Day subbasins by May 09 |
On track |
|
ORP CREP buffers (15) |
Establish 12 riparian buffers in Fifteenmile / Gorge Province by June 2009. |
On track |
|
ORP CREP buffers (ODA) |
Complete ODA CREP Technical Assistance Requirements
by June 2009. |
On track |
|
ORP Tech Assist Contacts |
Make 300 landowner/operator contacts by June 15, 2009 |
On track |
|
ORP Tech Assist Plans |
Write 26 new individual conservation plans / plan
revisions by June 15, 2009 |
On track |
|
ORP Tech Assist Practices |
Provide Technical Assistance implementing 40
practices benefiting water quality by June 2009 |
On track |
|
ORP Water
Quality (LMA) |
Implement |
On track |
|
WSP
Bakeoven Watershed |
Implement Bakeoven Watershed Action Plan through
June 2008 |
On track |
|
WSP Fifteenmile Watershed |
Implement the Fifteenmile Watershed Council
Action Plan through June 2009 |
On track |
|
WSP Mosier Watershed |
Implement the Mosier Watershed Action Plan through
June 2009 |
On track |
|
WSP Pine Hollow Watershed |
Assist |
On Hold |
|
WSP The Dalles Watershed |
Implement |
On track |
|
|
|
|
Each Goal pertains to an action plan which may have 6 or 60 individual tasks or actions